Reminder: Pavement Sealing Work Scheduled for Various Routes In Barton, Bates, Henry & Vernon Counties Beginning Week of July 27

Tentative schedule:
-
July 27-31: Missouri Route 43 between U.S. Route 160 near Liberal and U.S. Route 54 in Nevada
- August 3-7: Vernon County Route BB south of Nevada
- August 10-14: U.S. Route 52 between Interstate 49 and Bates County Route BB
- August 24-28: Missouri Route 18 between the Bates/Henry county line and the city limits of Clinton
Drivers can expect one-lane traffic with flaggers and pilot vehicles directing them through the work zone.
Drivers are urged to use caution and reduce their speed when traveling over recently-sealed sections of highways.
A chip-seal is planned for these roads as an economical way to maintain and preserve the roadway. The treatments keep a road from deteriorating and will extend its life.
Project information:
- Contractor: Hutchens Construction, Cassville
- Total cost: $1.1 million
- Completion date: September 4, 2015